We are leading the way toward sustainable growth, specializing in building bespoke, hyperscale data centers for the world.
The proposed facility, the PowerConneX New Albany Energy Center, project is a natural gas fired power generation facility located in New Albany, Licking County, Ohio.
The facility will be sited on approximately 48.6 acres and have a maximum total generating capacity of up to 120 megawatts. The purpose of the facility is to provide power using natural gas fired equipment that will serve as a primary source of electricity to a data center on the same site.
PowerConneX received its certificate authorizing construction of the project from the Ohio Power Sitting Board on July 22, 2025 (Case No. 25-90-EL-BLN).
Construction started in September 2025. Anticipate reaching commercial operations as early as Q3 2026.
Construction of the facility commenced in September 2025. The New Albany Energy Center is scheduled to reach operations by Q3 2026.
Email: pcxenergynewalbany@edgeconnex.com
Tel: +1 (703) 935-1980
Project contact information for project specific questions, communications, and general inquiries.
OPSB’s case number for the project is 25-90-EL-BGN. The filings made with the OPSB in the PowerConneX case can be viewed at this link. You may access all the filings in this case (including the application) on the OPSB website.
On April 23, 2025, PowerConneX hosted its first public information meeting.