New Albany Energy Center

EdgeConneX Powers the AI Revolution Sustainably

We are leading the way toward sustainable growth, specializing in building bespoke, hyperscale data centers for the world.

Project Summary

The proposed facility, the PowerConneX New Albany Energy Center, project is a natural gas fired power generation facility located in New Albany, Licking County, Ohio.

The facility will be sited on approximately 48.6 acres and have a maximum total generating capacity of up to 120 megawatts. The purpose of the facility is to provide power using natural gas fired equipment that will serve as a primary source of electricity to a data center on the same site.

PowerConneX received its certificate authorizing construction of the project from the Ohio Power Sitting Board on July 22, 2025 (Case No. 25-90-EL-BLN).

Project Status

Construction started in September 2025. Anticipate reaching commercial operations as early as Q3 2026.

Project Benefits

  1. Well paying, sustainable job growth: Creates significant direct and indirect jobs to the community and state of Ohio.
  2. State and local tax revenue: Contributes new tax revenue to support schools and community investment.
  3. Support for Ohio’s high-tech sector: Further bolsters Ohio’s high-tech corridor and substantiate the Columbus metros growing reputation as the silicon valley of the Midwest.
  4. Simplified infrastructure planning for AEP: Provides its own power solution, relieving AEP of the infrastructure burden.
Interactive Map
Anticipated Commercial Operation Date

Construction of the facility commenced in September 2025. The New Albany Energy Center is scheduled to reach operations by Q3 2026.


Project Contact Info

Email: pcxenergynewalbany@edgeconnex.com

Tel: +1 (703) 935-1980

Project contact information for project specific questions, communications, and general inquiries.


Application Request

OPSB’s case number for the project is 25-90-EL-BGN. The filings made with the OPSB in the PowerConneX case can be viewed at this link. You may access all the filings in this case (including the application) on the OPSB website.

Public Information Meeting Information

PIM #1

On April 23, 2025, PowerConneX hosted its first public information meeting.

PDF: 1st PIM Letter to Stakeholders PDF: 1st PIM Newspaper Notice
PIM #2

On April 24, 2025, PowerConneX Inc. hosted its second public information meeting.

PDF: 2nd PIM Letter to Stakeholders PDF: 2nd PIM Newspaper Notice