We are leading the way toward sustainable growth, specializing in building bespoke, hyperscale data centers for the world.
The proposed facility, the PowerConneX New Albany Energy Center, project is a natural gas fired power generation facility located in New Albany, Licking County, Ohio.
The facility will be sited on approximately 48.6 acres and have a maximum total generating capacity of up to 140 megawatts. The purpose of the facility is to provide power using natural gas fired equipment that will serve as a primary source of electricity to a data center on the same site.
PowerConneX received its certificate authorizing construction of the project from the Ohio Power Sitting Board on July 22, 2025 (Case No. 25-90-EL-BLN).
Construction started in September 2025 and is ongoing. Anticipate reaching commercial operations as early as September 2026, for the first engine set. Commercial operations will be fully reached for all engines by February 2027.
Construction of the facility commenced in September 2025. The New Albany Energy Center is scheduled to reach commercial operations for the first engine set by September 2026. Operations for all engines is expected to be reached as early as February 2027.
Email: pcxenergynewalbany@edgeconnex.com
Tel: +1 (703) 935-1980
Project contact information for project specific questions, communications, and general inquiries.
OPSB’s case number for the project is 25-90-EL-BGN. The filings made with the OPSB in the PowerConneX case can be viewed at this link. You may access all the filings in this case (including the application) on the OPSB website.
On April 23, 2025, PowerConneX hosted its first public information meeting.
PDF: 1st PIM Letter to Stakeholders (opens in new tab) PDF: 1st PIM Newspaper Notice (opens in new tab)On April 24, 2025, PowerConneX Inc. hosted its second public information meeting.